Installation (3.1L)
- Position generator to engine.
- Install positive battery lead to generator.
- Install generator output BAT terminal nut. Tighten generator output BAT terminal nut to 15 ft. lbs. (20 N.m).
- Install protective boot to generator output BAT terminal.
- Connect electrical connector to generator.
- Install generator bolts (2 & 3) to generator. See Figure .
- Install generator pivot bolt (1) to generator.
- Tighten generator bolts in order described. See TORQUE SPECIFICATIONS
. The following is a mandatory torque sequence:
- Tighten generator pivot bolt (1). See
- Tighten generator bolt (2).
- Tighten generator bolt (3).
- Install the generator rear brace nut (4). Tighten to specification. See TORQUE SPECIFICATIONS .
- Install coolant recovery reservoir.
- Install drive belt.
- Connect negative battery cable.
NOTE:
Do not tighten bolts.
NOTE:
Do not tighten bolt.