Test Description
The numbers below refer to the step numbers on the diagnostic table.
- 1: This step determines whether there is voltage at the battery and the high current source.
- 7: This step inspects for voltage at the ignition 1 source.
- 11: This step begins the check for voltage at the EBCM end of the ABS harness.
- 15: This step inspects for a defective ground connection.
- 16: This is an inspection for a defective EBCM connector.
| Step | Action | Values | Yes | No |
|---|---|---|---|---|
| 1 | Measure the voltage at the battery. Does the voltage measure within the specified range? |
11-14 V | Go to Step 3 | Go to Step 2 |
| 2 | Charge or replace the battery as required. Did you find and correct the condition? |
- | System OK | - |
| 3 | Inspect fuse EF2 in the engine fuse block. Is the fuse open? |
- | Go to Step 4 | Go to Step 8 |
| 4 |
|
- | Go to Step 6 | Go to Step 5 |
| 5 | Inspect the antilock brake system (ABS) function. Did you complete the action? |
- | System OK | - |
| 6 |
|
0 Ω | Go to Step 7 | Go to Step 25 |
| 7 | Repair the short to ground in circuit RD between terminal 1 of the engine fuse block connector C107 and the ABS harness EBCM connector. Did you complete the repair? |
- | System OK | - |
| 8 | Inspect fuse EF5 in the engine fuse block. Is the fuse open? |
- | Go to Step 9 | Go to Step 13 |
| 9 |
|
- | Go to Step 11 | Go to Step 10 |
| 10 | Inspect the ABS function. Did you find and correct the condition? |
- | System OK | - |
| 11 |
|
0 Ω | Go to Step 12 | Go to Step 25 |
| 12 |
|
- | System OK | - |
| 13 | Inspect fuse F11 in the I/P fuse block. Is the fuse open? |
- | Go to Step 14 | Go to Step 18 |
| 14 |
|
- | Go to Step 16 | Go to Step 15 |
| 15 | Inspect the ABS function. Is the repair complete? |
- | System OK | - |
| 16 |
|
0 Ω | Go to Step 17 | Go to Step 25 |
| 17 | Repair the short to ground in circuit PK fuse F11 of the I/P fuse block and terminal 15 of the ABS harness EBCM connector. Did you complete the repair? |
- | System OK | - |
| 18 |
|
11-14 V | Go to Step 20 | Go to Step 19 |
| 19 |
|
- | System OK | - |
| 20 | Measure the voltage between ground and terminal 15 of the EBCM connector. Does the voltage measure within the specified range? |
11-14 V | Go to Step 22 | Go to Step 21 |
| 21 |
|
- | System OK | - |
| 22 |
|
0 Ω | Go to Step 23 | Go to Step 26 |
| 23 | Test terminals 15, 19, 17, 18, and 16 of the EBCM connector. Is there a defective terminal? |
- | Go to Step 24 | Go to Step 25 |
| 24 | Repair the defective terminal or replace the connector or wiring harness as required. Did you complete the repair? |
- | System OK | - |
| 25 | Replace the ABS unit. Did you complete the replacement? |
- | System OK | - |
| 26 | Repair the defective ground connection. Did you complete the repair? |