Charging System Test
| Step | Action | Values | Yes | No |
|---|---|---|---|---|
| 1 | Did you review the Battery Description and Operation , the Starting System Description and Operation , and the Charging System Description and Operation and perform the necessary inspections? | - | Go to Step 2 | Go to Diagnostic Starting Point - Engine Electrical |
| 2 |
|
11-15.5 V | Go to Step 3 | Go to Battery Inspection/Test |
| 3 |
|
85 A | Go to Step 9 | Go to Step 4 |
| 4 |
|
0.5 V | Go to Step 6 | Go to Step 5 |
| 5 |
|
0.5 V | Go to Step 7 | Go to Step 8 |
| 6 | Test the battery positive circuit between the generator output terminal and the battery positive terminal for a high resistance. Refer to Circuit Testing
and Wiring Repairs
. Did you find and correct the condition? |
- | Go to Step 9 | Go to Step 7 |
| 7 | Repair the high resistance in the ground circuit between the generator housing and the battery negative terminal. Refer to Circuit Testing
and Wiring Repairs
. Did you complete the repair? |
- | Go to Step 9 | - |
| 8 | Replace the generator. Refer to Generator Replacement (1.6L) or Generator Replacement (1.8L/2.0L) . Did you complete the repair? |
- | Go to Step 9 | - |
| 9 | Operate the system in order to verify the repair. Did you correct the condition? |
- | System OK | Go to Step 3 |