Charging System Test
| Step | Action | Values | Yes | No |
|---|---|---|---|---|
| 1 | Did you review the Battery Description and Operation , the Starting System Description and Operation , and the Charging System Description and Operation and perform the necessary inspections? | - | Go to Step 2 | Go to Symptoms - Engine Electrical |
| 2 |
|
11-15.5 V | Go to Step 3 | Go to Testing for Intermittent Conditions and Poor Connections in Wiring Systems |
| 3 |
|
85 A | Go to Step 9 | Go to Step 4 |
| 4 |
|
0.5 V | Go to Step 6 | Go to Step 5 |
| 5 |
|
0.5 V | Go to Step 7 | Go to Step 8 |
| 6 | Test the battery positive circuit between the generator output terminal and the battery positive terminal for a high resistance. Refer to Circuit Testing
and Wiring Repairs
in Wiring Systems. Did you find and correct the condition? |
- | Go to Step 9 | Go to Step 7 |
| 7 | Repair the high resistance in the ground circuit between the generator housing and the battery negative terminal. Refer to Circuit Testing
and Wiring Repairs
in Wiring Systems. Did you complete the repair? |
- | Go to Step 9 | - |
| 8 | Replace the generator. Refer to Generator Replacement (1.6L) or Generator Replacement (1.8L/2.0L) . Did you complete the repair? |
- | Go to Step 9 | - |
| 9 | Operate the system in order to verify the repair. Did you correct the condition? |
- | System OK | Go to Step 3 |