Circuit/System Testing
- Vehicle OFF and all vehicle systems OFF. Disconnect the X2 harness connector at the X98 Hybrid/EV Battery Charger Receptacle. It may take up to 2 min for all vehicle systems to power down.
- Test for less than 10 Ω between the low reference terminal 3 and ground.
- Vehicle OFF, disconnect the X1 harness connector at the K114B Hybrid/EV Powertrain Control Module 2.
- Test for less than 2 Ω in the low reference circuit end to end.
- If 2 Ω or greater, repair the open/high resistance in the circuit.
- If less than 2 Ω, replace the K114B Hybrid/EV Powertrain Control Module 2.
- Go to next step: If less than 10 Ω
- Vehicle in Service Mode.
- Test for 4.8 - 5.2 V between the 5 V reference circuit terminal 1 and ground.
- Vehicle OFF, disconnect the X2 harness connector at the K114B Hybrid/EV Powertrain Control Module 2.
- Test for infinite resistance between the 5 V reference circuit and ground.
- If less infinite resistance, repair the short to ground on the circuit.
- Go to next step: If infinite resistance
- Test for less than 2 Ω in the 5 V reference circuit end to end.
- If 2 Ω or greater, repair the open/high resistance in the circuit.
- If less than 2 Ω, replace the K114B Hybrid/EV Powertrain Control Module 2.
- Vehicle OFF, disconnect the X2 harness connector at the K114B Hybrid/EV Powertrain Control Module 2. Vehicle in Service Mode.
- Test for less than 1 V between the 5 V reference circuit and ground.
- If 1 V or greater, repair the short to voltage on the circuit.
- If less than 1 V, replace the K114B Hybrid/EV Powertrain Control Module 2.
- Go to next step: If between 4.8 - 5.2 V
- Verify the scan tool DC Charge Port Lock Actuator Position Sensor parameter is less than 0.5 V.
- Vehicle OFF, disconnect the X1 harness connector at the K114B Hybrid/EV Powertrain Control Module 2. Vehicle in Service Mode.
- Test for less than 1 V between the signal circuit terminal 2 and ground.
- If 1 V or greater, repair the short to voltage on the circuit.
- If less than 1 V, replace the K114B Hybrid/EV Powertrain Control Module 2.
- Go to next step: If less than 0.5 V
- Install a 3 A fused jumper wire between the signal circuit terminal 2 and the 5 V reference circuit terminal 1.
- Verify the scan tool DC Charge Port Lock Actuator Position Sensor parameter is greater than 4.95 V.
- Vehicle OFF, remove the jumper wire. Disconnect the X1 harness connector at the K114B Hybrid/EV Powertrain Control Module 2.
- Test for infinite resistance between the signal circuit and ground.
- If less infinite resistance, repair the short to ground on the circuit.
- Go to next step: If infinite resistance
- Test for less than 2 Ω in the signal circuit end to end.
- If 2 Ω or greater, repair the open/high resistance in the circuit.
- If less than 2 Ω, replace the K114B Hybrid/EV Powertrain Control Module 2.
- Go to next step: If greater than 4.95 V
- Replace the X98 Hybrid/EV Battery Charger Receptacle.