Engine Assembly: Remove, Install, and Overhaul
WARNING: This page is about the Econoline E150, 4.2 2, which is a different variant/trim than selected.
Includes: Replace Rings, Main and Rod Bearings, Camshaft(s), Crankshaft and Timing Components. Remove Cylinder ridge, burnish Cylinders, grind Valves and clean and test or replace Lifters.
Includes (where applicable): Adjust Valves. DOES NOT include Pin fit or rebore and align Rods. See machine operations.| Applies To | Note | Standard Hours | Warranty Hours | Skill Level |
|---|---|---|---|---|
| V6 | 29.2 | A | ||
| Additional Procedure: ENGINE ASSEMBLY: Remove, Install, and Overhaul: | ||||
| V6, Where Air Cond interferes add | 1.4 | A | ||
| w/Frame Mounted Battery add | 0.2 | 0.2 | A | |
| Combination Procedure: OIL PUMP: Overhaul: | ||||
| V6 | 0.4 | B | ||