Floor Shift Assembly: Installation
HINT:
A bolt without a torque specification is shown in the standard bolt chart (see SPECIFIED TORQUE FOR STANDARD BOLTS ).
- INSTALL TRANSMISSION FLOOR SHIFT ASSEMBLY
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
- Install the floor shift with the 4 bolts.
Torque: 8.3 N*m (85 kgf*cm, 74 in.*lbf)
- Connect the 5 wire harness clamps to the floor shift.
- Connect the 2 connectors.
- Install the floor shift with the 4 bolts.
- CONNECT FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY
- Temporarily connect the shifting rod to the connecting rod swivel with the nut.
HINT:
The nut will be tightened to a torque specification during the shift lever position adjustment procedure.
- Temporarily connect the shifting rod to the connecting rod swivel with the nut.
- INSTALL NO. 1 CONSOLE BOX DUCT
- Install the duct with the 2 screws.
- INSTALL CONSOLE BOX ASSEMBLY
- Install the console box (see INSTALLATION ).
- ADJUST SHIFT LEVER POSITION
- Adjust the shift lever position (see ADJUSTMENT ).
- INSPECT SHIFT LEVER POSITION
- Inspect the shift lever position (see ON-VEHICLE INSPECTION ).
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
- INSTALL COWL TOP VENTILATOR LOUVER (See INSTALLATION )
- PERFORM INITIALIZATION
- Perform initialization (see
INITIALIZATION
).NOTE: Certain systems need to be initialized after disconnecting and reconnecting the cable from the negative (-) battery terminal.
- Perform initialization (see
INITIALIZATION
).