Charging System: Generator: Installation
- INSTALL GENERATOR
- Using an E8 "TORX" socket wrench, set the generator with the 2 stud bolts.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- Install the generator with the 2 bolts and 2 nuts.
Torque: 43 N*m (438 kgf*cm, 32 ft.*lbf)
- Install the wire harness bracket with the nut
Torque: 6.0 N*m (61 kgf*cm, 53 in.*lbf)
- Connect the harness to the +B terminal with nut A.
Torque: 12 N*m (122 kgf*cm, 9 ft.*lbf)
- Install the oil cooler tube with bolt B.
Torque: 14 N*m (140 kgf*cm, 10 ft.*lbf)
- Connect wire harness clamp C.
- Connect generator connector D.
- Using an E8 "TORX" socket wrench, set the generator with the 2 stud bolts.
- INSTALL FRONT STABILIZER BAR
- Install the front stabilizer bar (See INSTALLATION ).
- INSTALL WIRE HARNESS
- Connect the wire harness with the bolt and clamp
Torque: 21 N*m (214 kgf*cm, 15 ft.*lbf)
- Connect the wire harness with the bolt and clamp
- INSTALL V-RIBBED BELT (See INSTALLATION )
- INSTALL RADIATOR RESERVE TANK ASSEMBLY (See INSTALLATION )
- INSTALL AIR CLEANER CASE SUB-ASSEMBLY (See INSTALLATION )
- INSTALL AIR CLEANER CAP SUB-ASSEMBLY (See INSTALLATION )
- INSTALL NO. 1 AIR CLEANER INLET (See INSTALLATION )
- INSTALL REAR ENGINE UNDER COVER LH
- INSTALL REAR ENGINE UNDER COVER RH
- INSTALL ENGINE UNDER COVER
- INSTALL ENGINE ROOM SIDE COVER RH (See INSTALLATION )
- INSTALL COOL AIR INTAKE DUCT SEAL (See INSTALLATION )
- INSTALL FRONT WHEELS
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE: When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See INITIALIZATION ).