Electric Power Steering Gearbox: Installation

CAUTION:
  • When raising the transmission jack, make sure that the tie-rod end and the drive shaft boot do not interfere. The drive shaft boot may be damaged.
  • For parts which are not reusable, always use new parts.
  1. Install the steering gearbox assembly and stiffener to the crossmember COMPL.
    CAUTION: Always use new bolts, since the mounting bolts of the steering gearbox assembly are lubricated.

    Tightening torque: 

    Refer to "COMPONENT" of "General Description" for the tightening torque, Ref. to POWER ASSISTED SYSTEM (POWER STEERING)>GENERAL DESCRIPTION>COMPONENT>STEERING GEARBOX .

  2. Install the power steering harness connector and harness clamp.
  3. Install the universal joint assembly steering. Ref. to POWER ASSISTED SYSTEM (POWER STEERING)>UNIVERSAL JOINT>INSTALLATION .
  4. Connect the tie-rod ends.
    CAUTION: Do not apply grease, etc. to the tapered portion of ball joint.
    1. Tighten the castle nut.

      Tightening torque: 

      27 N.m (2.8 kgf-m, 19.9 ft-lb)

      NOTE: If the ball stud hole and the cutout portion of the castle nut are not aligned after tightening, tighten the castle nut within the range of 60° to align with each other.
    2. Install a new cotter pin.
  5. Install the stabilizer. Ref. to FRONT SUSPENSION>STABILIZER>INSTALLATION>STABILIZER .
  6. Install the front exhaust pipe, Ref. to EXHAUST (H4DO)>FRONT EXHAUST PIPE>INSTALLATION .
  7. Install the crossmember support front and the crossmember support rear, Ref. to FRONT SUSPENSION>CROSSMEMBER SUPPORT>INSTALLATION .
  8. Install the under cover front.

    Tightening torque: 

    18 N.m (1.8 kgf-m, 13.3 ft-lb)

  9. Install the front wheels and lower the vehicle.

    Tightening torque: 

    120 N.m (12.2 kgf-m, 88.5 ft-lb)

  10. Connect the battery ground terminal. Ref. to REPAIR CONTENTS>NOTE>BATTERY>GROUND TERMINAL REMOVAL OR INSTALLATION .
  11. After adjusting toe-in and steering angle, tighten the lock nut on tie-rod end.
    CAUTION:

    Tightening torque: 

    85 N.m (8.7 kgf-m, 62.7 ft-lb)

    NOTE: When adjusting toe-in, hold the boot steering gearbox as shown to prevent it from being rotated or twisted. If it becomes twisted, straighten it.
    G11245602Courtesy of SUBARU OF AMERICA, INC.