AT Shift Lock Solenoid And "P" Range Switch: Inspection
- CHECK SOLENOID UNIT.
Measure the resistance of solenoid unit connector terminals.
Terminals
No. 4 - No. 3:
Is the resistance 27.6 - 30.5 Ω?
Yes: Go to 2.
No: Replace the solenoid unit. Refer to CONTROL SYSTEMS>AT SHIFT LOCK SOLENOID AND "P" RANGE SWITCH .
- CHECK SOLENOID UNIT.
Connect the battery to the solenoid unit connector terminals, and then operate the solenoid.
Terminals
No. 3 (+) - No. 4 (-):
Does the solenoid unit operate normally?
Yes: Go to 3.
No: Replace the solenoid unit. Refer to CONTROL SYSTEMS>AT SHIFT LOCK SOLENOID AND "P" RANGE SWITCH .
- CHECK "P" RANGE SWITCH.
- Shift the select lever to "P" range.
- Measure the resistance between "P" range switch connector terminals.
Terminals
No. 1 - No. 2:
Is the resistance less than 1 Ω?
Yes: Go to 4.
No: Replace the "P" range switch. Refer to CONTROL SYSTEMS>AT SHIFT LOCK SOLENOID AND "P" RANGE SWITCH .
- CHECK "P" RANGE SWITCH.
- Set the select lever to other than "P" range.
- Measure the resistance between "P" range switch connector terminals.
Terminals
No. 1 - No. 2:
Is the resistance 1 MΩ or more?
Yes: Normal.
No: Replace the "P" range switch. Refer to CONTROL SYSTEMS>AT SHIFT LOCK SOLENOID AND "P" RANGE SWITCH .