Before Overhaul

  1. Remove the torque converter. Ref. to CONTINUOUSLY VARIABLE TRANSMISSION (TR690)>TORQUE CONVERTER>REMOVAL .
  2. Remove the air breather hose. Ref. to CONTINUOUSLY VARIABLE TRANSMISSION (TR690)>AIR BREATHER HOSE>REMOVAL .
  3. Attach the ST.
    NOTE: When attaching the ST to the (a) positions, spacers or similar of 2.0 mm (0.08 in) or more in thickness are necessary.

    Preparation tool: 

    ST: STAND ASSY (18632AA000)

    G13225799Courtesy of SUBARU OF AMERICA, INC.
  4. Place the transmission body.
    CAUTION: Prepare a container for draining of oil, because CVTF remaining inside the transmission body may flow out from the input shaft portion.