Removal & Installation

Applies ToNoteStandard HoursWarranty HoursSkill Level
RWD,In-Line4,5 Spd Trans,Gas3.6C
Combination Procedure: BEARING RETAINER SEAL: Remove & Replace:
0.4B
Combination Procedure: CLUTCH PRESSURE PLATE: Remove & Replace:
0.3C
Combination Procedure: CLUTCH RELEASE BEARING: Remove & Replace:
0.2C
Combination Procedure: EXTENSION HOUSING SEAL: Remove & Replace:
0.1B
Combination Procedure: FLYWHEEL: Remove & Replace:
0.5C
Combination Procedure: INPUT SHAFT BEARING: Remove & Replace:
5 Spd Trans, Front1.8A
Combination Procedure: TRANSFER CASE ASSEMBLY: Overhaul:
In-Line4, RF1A Type Transfer4.4A
In-Line4, VF1A Type Transfer5.5A
Combination Procedure: TRANSMISSION ASSEMBLY: Replace:
0.4C