Skid Control Ecu: Installation
- INSTALL SKID CONTROL ECU
- Install the skid control ECU with the 3 nuts.
Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf)
- Connect the 4 skid control ECU connectors.
- Install the wire harness clamp and skid control buzzer to the skid control ECU bracket.
- Install the skid control ECU with the 3 nuts.
- INSTALL STEERING COLUMN ASSEMBLY
- Install the steering column (see
INSTALLATION
).
HINT:
Refer to the procedures from the installation of the steering column assembly up until the installation of the No 2. rear floor board.
- Install the steering column (see
INSTALLATION
).
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
- INSPECT SRS WARNING LIGHT (See REMOVAL )
- PERFORM INITIALIZATION
- Perform initialization (see
INITIALIZATION
).NOTE: Certain systems need to be initialized after disconnecting and reconnecting the cable from the negative (-) battery terminal.
- Perform initialization (see
INITIALIZATION
).
- PERFORM SYSTEM INITIALIZATION
- Perform the brake system initialization (see INITIALIZATION ).
- PERFORM YAW RATE SENSOR ZERO POINT CALIBRATION
- Perform the yaw rate sensor zero point calibration (see CALIBRATION ).
- CHECK AND CLEAR DTC
- Check and clear the DTCs (see DTC CHECK / CLEAR ).