Commutator Test
- Ensure continuity exists between any 2 commutator segments. If continuity does not exist, replace armature.
- Clean commutator segment surfaces with No. 400 grit sandpaper (if necessary). If surface is scored, out-of-round, or pitted, replace commutator.
- Using "V" blocks and dial indicator, ensure maximum commutator runout and minimum commutator diameter does not exceed specifications. See STARTER SPECIFICATIONS
.