Auxiliary Climate Control Assembly: Installation

WARNING: This page is about a different car, the 2013 Land Rover LR4, 2012 Land Rover LR4, 2011 Land Rover LR4, and 2010 Land Rover LR4. However, it is still accessible from the selected car via links, so may be relevant.
  1. Install the climate control assembly.
    • Tighten the bolts to 10 Nm (7 lb.ft).
    • Connect and secure the electrical connectors.
  2. Install the sealing plate.
    • Tighten the bolts to 10 Nm (7 lb.ft).
  3. Connect and secure the coolant hoses.
    • Secure the clips.
    • Remove the hose clamps.
  4. Connect the A/C pipes.
    • Clean the component mating faces.
    • Install the O-ring seals.
    • Tighten the 2 bolts to 10 Nm (7 lb.ft).
  5. Install the heat shield.
    • Tighten the 4 nuts.
  6. Secure the exhaust mountings.
  7. Fill the A/C system. Refer to Air Conditioning (A/C) System Recovery, Evacuation and Charging article.
  8. Install the C-pillar lower trim panel. Refer to C-Pillar Lower Trim Panel article.
  9. Connect the battery ground cable. Refer to Specifications article.
  10. Install the spare wheel and tire.
    • Stow the tool kit.
  11. Connect the exhaust extraction hoses to the tail pipes.
  12. Remove the coolant expansion tank cap.
    • Top-up the coolant.
  13. Start and run the engine.
    • Hold the engine speed at 2, 500 RPM for 30 seconds.
    • Return the engine to idle for 30 seconds.
    • Repeat the above procedure a further four times.
  14. NOTE: When the coolant bleed is complete and prior to installing the expansion tank cap, top up the expansion tank 30mm above the maximum level.
  15. Install the coolant expansion tank cap.
  16. Run the engine until the thermostat opens.
  17. Switch the engine off and allow to cool.
  18. Check and top-up the coolant if required.
    GJ0013757