Installation [08/2014 - ]: Procedure
- INSTALL RADIO RECEIVER ASSEMBLY
- INSTALL NO. 2 RADIO BRACKET
- Install the No. 2 radio bracket with the 4 screws.
- INSTALL NO. 1 RADIO BRACKET
- Install the No. 1 radio bracket with the 4 screws.
- INSTALL DCM (TELEMATICS TRANSCEIVER) WITH BRACKET (w/ Manual (SOS) Switch)
Refer to PROCEDURE - Step 3
- INSTALL RADIO RECEIVER ASSEMBLY WITH BRACKET
- Connect each connector.
- Install the radio receiver assembly with bracket with the 4 bolts.
- INSTALL AIR CONDITIONING CONTROL ASSEMBLY
Refer to PROCEDURE - Step 3
- INSTALL INTEGRATION CONTROL AND PANEL ASSEMBLY
Refer to PROCEDURE - Step 17
- INSTALL UPPER CONSOLE PANEL SUB-ASSEMBLY
Refer to PROCEDURE - Step 22
- INSTALL UPPER NO. 1 CONSOLE PANEL GARNISH
Refer to PROCEDURE - Step 23
- INSTALL UPPER NO. 2 CONSOLE PANEL GARNISH
Refer to PROCEDURE - Step 24
- INSTALL LOWER CENTER INSTRUMENT PANEL FINISH PANEL
Refer to PROCEDURE - Step 7
- INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY
Refer to PROCEDURE - Step 18
- INSTALL NO. 3 INSTRUMENT CLUSTER FINISH PANEL GARNISH (for Metal Finish Panel and Urethane Panel)
Refer to PROCEDURE - Step 21
- INSTALL NO. 3 INSTRUMENT CLUSTER FINISH PANEL GARNISH (for Wood Panel and Bamboo Panel)
Refer to PROCEDURE - Step 22
- INSTALL INSTRUMENT SIDE PANEL RH
Refer to PROCEDURE - Step 29
- INSTALL FRONT DOOR OPENING TRIM WEATHERSTRIP RH
Refer to PROCEDURE - Step 51
- CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL NOTE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See article. Refer to INITIALIZATION [08/2014 - 08/2015] Refer to INITIALIZATION [08/2015 - ] ).
- INSTALL REAR FLOOR BOARD UPPER NO. 3 PLATE
Refer to PROCEDURE - Step 69
- INSTALL DECK FLOOR BOX RH
Refer to PROCEDURE - Step 70
- INSTALL REAR NO. 3 FLOOR BOARD
Refer to PROCEDURE - Step 71
- INSTALL REAR DECK FLOOR BOX
Refer to PROCEDURE - Step 72
- INSTALL REAR NO. 2 FLOOR BOARD
Refer to PROCEDURE - Step 73
- REPLACED OPERATION (w/ Parking Assist Monitor System)
(See article. Refer to INITIALIZATION [08/2014 - 08/2015] Refer to INITIALIZATION [08/2015 - ] )