Circuit/System Verification

  1. Engine running measure and record the voltage at the battery terminals. Verify that the battery voltage is 12.6-15.5 volts.
  2. Observe the scan tool EBCM battery positive voltage parameter. The reading should be between 12.6 and 15.5 volts.


  1. Engine running measure and record the voltage at the battery terminals. Verify that the battery voltage is 12.6-15.5 volts.
  2. Observe the scan tool EBCM battery positive voltage parameter. The reading should be between 12.6 and 15.5 volts.
  1. Ignition OFF, disconnect the harness connector at the EBCM.
  2. Ignition OFF and scan tool disconnected, open and close the driver door, and wait 1 minute. Test for less than 5 ohms between the ground circuit terminal 16 and ground:
    • If greater than the specified range, test the ground circuits for an open/high resistance.
  3. Ignition ON, verify a test lamp illuminates between the IGN / B+ circuit terminals listed below and ground.
    • B+ Terminal 1
    • B+ Terminal 32
    • IGN Terminal 8
    • If the test lamp did not illuminate, test the IGN / B+ circuits for a short to ground or an open/high resistance.
  4. If the circuits test normal, replace the EBCM.