Circuit figure
Inspection steps
- Transmission wire unit check (lock-up control solenoid (SLU))
- Disconnect the connector L4 of the transmission wire.
- Measure the resistance between the terminals.RESISTANCE SPECIFICATIONS
Inspection terminals Inspection conditions Standard value L4-12 (SLU+) - L4-4 (SLU-) 20°C 5.0 to 5.6 Ω L4-12 (SLU+) - chassis ground Always 10 k Ωor more L4-4 (SLU-) - chassis ground Always 10 k Ωor more - Connect the connector L4 of the transmission wire.
NG: go to step 4.
OK: Go to next step.
- Check wiring harness and connector (transmission wire - transmission control computer)
- Disconnect the connector A18 of the transmission control computer ASSY.
- Measure the resistance between the terminals.RESISTANCE SPECIFICATIONS
Inspection terminals Inspection conditions Standard value A18-13 (SLU+) - A18- 1 (SLU-) 20°C 5.0 to 5.6Ω A18-13 (SLU+) - chassis ground Always 10 k Ωor more A18-1 (SLU-) - chassis ground Always 10 k Ωor more - Connect the connector A18 of the transmission control computer ASSY.
NG: Repair or replacement of wiring harness or connector
OK: Go to next step.
- Replacement of transmission control computer ASSY
- Replace the transmission control computer ASSY. (Refer to Transmission control computer ASSY )
Next: AT unit correction (refer to Inspection for problems that do not normally occur )
- Check of lock-up control solenoid (SLU) unit
- Check the lock-up control solenoid (SLU) unit. (Refer to Neutral start switch ASSY )
NG: Repair or replacement of transmission valve body ASSY (refer to Transmission valve body ASSY )
OK: Repair or replacement of transmission wire (refer to Transmission wire )