Main Relay: Inspection
- Check that there is no deformation, cracks or other damages.
- Check the resistance between terminals.
Courtesy of SUBARU OF AMERICA, INC.
|
| Terminals No. |
Inspection conditions |
Standard |
| 1 - 3 |
Always |
1 MΩ or more |
| 1 - 3 |
Apply battery voltage between terminals 2 and 4. |
Less than 1 Ω |