Component Testing
AIR pump Dynamic Test
- Install a 50-amp fused jumper wire between the B+ terminal and 12 volts. Install a jumper wire between the ground terminal and ground.
- Observe for a pressurized air flow at the pump outlet.
- If a pressurized air flow is not observed, replace the AIR pump.
Relay Test
- Test between the normally closed switch terminals, if any, for 0 ohms.
- Test between the normally open switch terminals for infinite ohms.
- Test between each switch terminal and either coil terminal for infinite ohms.
- Connect the relay coil terminals to ground and fused power to energize the relay.
- Test between each switch terminal and each coil terminal for 0 volts.
- Test between the normally closed switch terminals, if any for infinite ohms.
- Test between the normally open switch terminals for 0 ohms.