Shift Schedules

WARNING: This page is about a different car, the 2006 Dodge Magnum, 2006 Dodge Charger, and 2006 Chrysler 300. However, it is still accessible from the selected car via links, so may be relevant.

As mentioned earlier, the TCM has programming that allows it to select a variety of shift schedules. Shift schedule selection is dependent on the following:

As driving conditions change, the TCM appropriately adjusts the shift schedule. Refer to the following chart to determine the appropriate operation expected, depending on driving conditions.

Schedule  Condition  Expected Operation 
Extreme Cold  Oil temperature below -16° F -Park, Reverse, Neutral and 1st and 3rd gear only in D position, 2nd gear only in Manual 2 or L
-No EMCC
Super Cold  Oil temperature between -12° F and 10° F - Delayed 2-3 upshift
- Delayed 3-4 upshift
- Early 4-3 coastdown shift
- High speed 4-2, 3-2, 2-1 kickdown shifts are prevented
-Shifts at high throttle openings will be early.
- No EMCC
Cold  Oil temperature between 10° F and 36° F -Shift schedule is the same as Super Cold except that the 2-3 upshifts are not delayed.
Warm  Oil temperature between 40° F and 80° F - Normal operation (upshift, kickdowns, and coastdowns)
- No EMCC
Hot  Oil temperature between 80° F and 240° F - Normal operation (upshift, kickdowns, and coastdowns)
- Normal EMCC operation
Overheat  Oil temperature above 240° F or engine coolant temperature above 244° F - Delayed 2-3 upshift
- Delayed 3-4 upshift
- 3rd gear FEMCC from 30-48 mph
- 3rd gear PEMCC above 35 mph
- Above 25 mph the torque converter will not unlock unless the throttle is closed or if a wide open throttle 2nd PEMCC to 1 kickdown is made