Connector-Coolant Outlet: Installation: Installation-2.7L

Fig 1: View Of Coolant Outlet Connector - 2.7L
GC0058768Courtesy of CHRYSLER LLC
1 - BOLT (2)
2 - BOLT (2)
3 - COOLANT OUTLET CONNECTOR
  1. Clean sealing surfaces. Inspect gaskets for tears and cuts. Replace as necessary.
  2. Install coolant outlet connector and tighten bolts to 12 N.m (105 in. lbs.).
  3. Connect hoses at coolant outlet connector.
  4. Connect engine coolant temperature sensor connector.
  5. Install upper intake manifold. Refer to appropriate Engine SERVICE INFORMATION article.
  6. Fill cooling system. See STANDARD PROCEDURE .


Fig 1: Identifying Coolant Outlet Connector - 2.7L
GC0031148Courtesy of CHRYSLER LLC
1 - BOLT (2)
2 - BOLT (2)
3 - COOLANT OUTLET CONNECTOR
  1. Clean sealing surfaces. Inspect gaskets for tears and cuts. Replace as necessary.
  2. Install coolant outlet connector and tighten bolts to 12 N.m (105 in. lbs.).
  3. Connect hoses at coolant outlet connector.
  4. Connect engine coolant temperature sensor connector.
  5. Install upper intake manifold. Refer to appropriate Engine SERVICE INFORMATION article.
  6. Fill cooling system. See STANDARD PROCEDURE .