(Transmission Control Module (TCM) Removal And Installation)
ABBREVIATED PROCEDURE
| Work | H/W | Tightening torque N.m (kgf.m/lb-ft) | SST/Equipment | Chemical | etc | |
|---|---|---|---|---|---|---|
|
||||||
| 1 | Perform the oil pressure characteristics backup procedure using the diagnostic tool when replacing with a new TCM | - | - | Diagnostic tool | - | Refer to appropriate service information |
| 2 | Disconnect the negative (-) battery cable | - | - | - | - | - |
| 3 | Disconnect the TCM connectors | - | - | - | - | - |
| 4 | Remove the TCM bracket assembly after removing the bolts and nut | Bolt Nut | 9.8 - 11.8 (1.0 - 1.2/7.2 - 8.7) | - | - | - |
| 5 | Remove the TCM from the bracket after removing the bolts | Bolt | 9.8 - 11.8 (1.0 - 1.2/7.2 - 8.7) | - | - | - |
|
||||||
| Install in the reverse order of removal | Refer to appropriate service information | |||||
|
||||||
|
||||||