Installation - Engine
Courtesy of CHRYSLER LLC
| 1 - Bolts |
| 2 - Engine Lift Fixture |
| 3 - Adapter Bolt |
| 4 - Adapter |
| 5 - Adapter Nut |
- Install engine lift fixture Special tool # 8984 and 8984-UPD.
- Position the engine in the engine compartment.
- Lower engine into compartment and align engine with transmission.
Courtesy of CHRYSLER LLC
| 1 - ENGINE |
| 2 - BOLTS |
| 3 - TRANSMISSION |
- Mate engine (1) and transmission (3) and install two transmission to engine block mounting bolts (2) finger tight.
Courtesy of CHRYSLER LLC
- Lower engine assembly until the engine mounts (2) rests in frame perches (1).
Courtesy of CHRYSLER LLC
| 1 - ENGINE |
| 2 - BOLTS |
| 3 - TRANSMISSION |
Courtesy of CHRYSLER LLC
- Install remaining transmission to engine block mounting bolts (2) and the oil pan to transmission bolts (1) and tighten.
Courtesy of CHRYSLER LLC
- Install and tighten engine mount to frame bolts (3) and nuts.
Courtesy of CHRYSLER LLC
- Install drive plate to torque converter bolts (1).
Courtesy of CHRYSLER LLC
| 1 - STRUCTURAL COVER |
| 2 - BOLTS |
- Install the structural dust cover (1).
Courtesy of CHRYSLER LLC
- Install the starter (1) and connect the starter wires. Refer to INSTALLATION
.
- Install exhaust pipe to manifold.
- Lower the vehicle.
Courtesy of CHRYSLER LLC
| 1 - Bolts |
| 2 - Engine Lift Fixture |
| 3 - Adapter Bolt |
| 4 - Adapter |
| 5 - Adapter Nut |
- Remove engine lift fixture (2), special tool # 8984 and 8984-UPD.
Courtesy of CHRYSLER LLC
| 1 - Heater Hose |
| 2 - Clamp |
| 3 - Tube |
Courtesy of CHRYSLER LLC
| 1 - Heater Hose |
| 2 - Clamp |
| 3 - Tube |
- Connect the fuel supply line. Refer to STANDARD PROCEDURE
.
- Reinstall the power steering pump.
- Connect the heater hoses (1).
Courtesy of CHRYSLER LLC
- Reconnect the ground wires to the rear of each cylinder head.
- Install the intake manifold. See INSTALLATION .
- Install the generator (2), and wire connections. Refer to INSTALLATION
.
Courtesy of CHRYSLER LLC
- Install a/c compressor (3). Refer to INSTALLATION
.
Courtesy of CHRYSLER LLC
| 1 - GENERATOR |
| 2 - IDLER PULLEY |
| 3 - WATER PUMP |
| 4 - P/S PUMP |
| 5 - A/C COMPRESSOR |
| 6 - CRANKSHAFT |
| 7 - BELT TENSIONER |
- Install the accessory drive belt. Refer to INSTALLATION
.
- Install the radiator fan shroud. Refer to INSTALLATION
.
- Connect the radiator lower hose.
- Connect the transmission oil cooler lines to the radiator.
- Connect the radiator upper hose.
Courtesy of CHRYSLER LLC
- Install the air cleaner resonator and duct work.
- Add engine oil to crankcase. Refer to SPECIFICATIONS
.
- Fill cooling system. Refer to STANDARD PROCEDURE
.
- Install the engine cover (1).
Courtesy of CHRYSLER LLC
- Install the strut tower support (1).
- Connect battery negative cable.
- Start engine and inspect for leaks.
- Road test vehicle.