Transmission Control Cable: Installation
- INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY
- Install the transmission control cable assembly with the 2 nuts and bolt.
Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf)
- Install the transmission control cable assembly to the control cable bracket with 2 new clips.
- Install the transmission control cable assembly to the transaxle with the 2 clips.
- Connect the control cable to the shift lever retainer.CAUTION:
- The projecting part of the cable outer should face outside when the shift cable is connected.
- After installation, make sure that the cable outer lock is projecting from A as shown in the illustration.
- Install the control select cable to the shift lever assembly.
- Install the control shift cable to the shift lever assembly.
- Install the transmission control cable assembly with the 2 nuts and bolt.
- ADJUST TRANSMISSION CONTROL SELECT CABLE (See ADJUSTMENT )
- INSTALL INSTRUMENT PANEL FINISH LOWER PANEL (See INSTALLATION )
- INSTALL FRONT NO. 2 CONSOLE BOX INSERT (See INSTALLATION )
- INSTALL FRONT NO. 1 CONSOLE BOX INSERT (See INSTALLATION )
- INSTALL INSTRUMENT CLUSTER FINISH CENTER LOWER PANEL (See INSTALLATION )
- INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY (See INSTALLATION )
- INSTALL NO. 1 FRONT FLOOR HEAT INSULATOR
- Install the No. 1 front floor heat insulator with the 3 nuts.
Torque: 5.5 N*m (56 kgf*cm, 49 in.*lbf)
- Install the No. 1 front floor heat insulator with the 3 nuts.
- INSTALL CENTER EXHAUST PIPE ASSEMBLY (See INSTALLATION )
- INSTALL FRONT FLOOR CENTER BRACE (See INSTALLATION )
- INSTALL AIR CLEANER ASSEMBLY (See INSTALLATION )
- INSPECT FOR EXHAUST GAS LEAK